Essex North Shore Agricultural & Technical School – Danvers, Massachusetts
Summary
This project transformed a 1972 heating system by replacing aging steam boilers with an electrified geothermal system, made possible through Inflation Reduction Act funding. The $4 million project upgraded the school’s outdated steam heating system to modern geothermal technology that uses the Earth’s constant underground temperature to efficiently heat and cool campus buildings. The result is a 50-year renewable energy system that dramatically reduces carbon emissions, lowers energy costs, and provides students with a “living lab” for hands-on technical education.
The geothermal project includes ten wells drilled 750 feet into bedrock, circulating water through a closed-loop system that maintains efficient heating and cooling year-round. The system can efficiently heat the building even on sub-zero days and provides cooling in the summer, all while reducing reliance on fossil fuels. In addition to reducing emissions, the geothermal system serves as an educational tool for students in Essex Tech’s HVAC and environmental programs. The former boiler room has been transformed into a “living lab,” a space where students in HVAC and environmental technology programs can study cutting-edge renewable systems firsthand.
The facility’s design, including color-coded pipe insulation and an interactive HVAC controls system, allows students to study renewable energy technology in real time, preparing them for careers in the growing clean energy sector.
“This project turns our mechanical room into a classroom,” said Assistant Superintendent and Principal Shannon Donnelly. “Our students will graduate not only understanding the technology but ready to build and maintain the sustainable systems of tomorrow.”
Location
Danvers, MA
“EEI didn’t just come in with a presentation—they came in as partners. They sat down, talked to us like people, and truly listened to our needs. We chose them over global corporations because they understood our mission, our students, and our long-term vision. That decision has paid dividends.”
Highlights
- Funding Support: $1.8 million federal tax rebate secured through the Inflation Reduction Act and $160k in Mass Save incentives
- Total Cost financed by the school was $3.2M after more than 50% of the cost was funded through grants, rebates, and donor support
- The geothermal system will save more than $4M in energy costs over 20 years
- The average lifespan of a geothermal system is 50 years
- The geothermal system and boiler room were designed to double as a living lab for Essex students to gain practical experience in HVAC and renewable technologies
“This room is my baby. It’s not just an energy system—it’s a classroom. Our students can learn how real-world sustainability works right here.”
–Ryan Monks, Director of Facilities, Farm, and Grounds